Phase 1 of the Charlotte Gateway Station Project represents completion of the railroad infrastructure needed to access the Charlotte Gateway Station & District by passenger rail. The North Carolina Department of Transportation is leading the Phase 1 design and construction.

Charlotte
Gateway
Station
Phase 1

Phase 1: Track, Structures and Signals (TS&S) & Intercity Rail Platform Project Details

  • Two 2,000 foot long station tracks located between 8th Street and 3rd Street
  • Signals to govern train operations
  • 5 new railroad bridges at West 4th Street, West Trade Street, West 5th Street and West 6th  Street and at the Bank of America greenway
  • 1,100 foot long ADA compliant, high-level passenger boarding platform and canopy foundations

Phase 1 will:

  • Separate passenger trains from freight operations
  • Improve freight traffic flow to the intermodal facility at Charlotte Douglas International Airport
  • Include a connection to NCDOT's new Charlotte Yard where train maintenance will occur

Project start date: Construction began in July 2018
Project completion: September 2022
Contractor: Crowder Construction Company
Cost: $80-90 million; Funded through a combination of local, state and federal funds including $30 million via Federal TIGER Grant

Project Contacts

CATS
Brian Nadolny
Infrastructure Project Manager
704-999-1372
bnadolny@ci.charlotte.nc.us

NCDOT – Rail Division
Craig M. Newton, P.E.
Facilities Engineer
919-707-4731
cmnewton@ncdot.gov